- SAP PM - Home
- SAP PM - Overview
- SAP PM - Technical Objects
- SAP PM - Equipment Master Record
- Functions of Technical Objects
- SAP PM - Creating Multilingual Text
- SAP PM - Breakdown Maintenance
- SAP PM - Corrective Maintenance
- SAP PM - Creating/Planning MO
- SAP PM - Preventive Maintenance
- SAP PM - Maintenance Planning
- Project Oriented Maintenance
- SAP PM - Refurbishment Process
- SAP PM - Warranty Claim Processing
- Mobile Applications For EAM
- Work Clearance Management
- SAP PM - Information System
- Cross Application Time Sheet
- SAP PM - Single & Composite Roles
SAP PM Online Quiz
Following quiz provides Multiple Choice Questions (MCQs) related to SAP PM. You will have to read all the given answers and click over the correct answer. If you are not sure about the answer then you can check the answer using Show Answer button. You can use Next Quiz button to check new set of questions in the quiz.
Q 1 - In Plant Maintenance, arrange the following tasks in correct order?
Notification
Newly Created Work Order
Creation of Purchase request for work orders
Purchase Order created and parts Received
Parts issues to Work Order
Approval and Planning of Work Order
Answer : D
Explanation
Key Steps that are included as part of Work Order Notification under SAP PM −
- Notification
- Newly Created Work Order
- Creation of Purchase request for work orders
- Purchase Order created and parts Received
- Parts issues to Work Order
- Approval and Planning of Work Order
- Scheduling and Releasing Work Order
- Work Order Execution
- Closing a Work Order
Q 2 - Which of the following T-code is used to change the Notification?
Answer : B
Q 3 - Which of the following is incorrect about Maintenance strategy in Plant Maintenance?
A - Maintenance strategies are optional.
B - A maintenance strategy defines the rules for the sequence of planned maintenance work.
D - Maintenance strategy is required to be defined with a multiple counter plan.
Answer : D
Q 4 - Which of the following maintenance is suitable to plan annual maintenance of a car or service of a Printer after 1 million copies?
Answer : A
Explanation
Single cycle maintenance plan is used to define exactly one time-based or performance-based maintenance cycle, in which you specify the interval at which the maintenance plan should be executed.
It is one of the simplest maintenance plan used for Maintenance planning.
Example
A single cycle maintenance plan- annual maintenance of a car or service of a Printer after 1 million copies.
Q 5 - In SAP Plant Maintenance, Refurbishment process is integrated with MM, CP and PS?
Answer : A
Q 6 - In Refurbishment process, to move the material to Warehouse which of the following movement type is created?
Answer : A
Q 7 - Which of the following module is integrated with Plant Maintenance to perform Order settlement to a project or WBS element?
Answer : B
Q 8 - Which of the time based scheduling allows you to perform Maintenance strategy every 30 working days?
Answer : C
Explanation
Time-based (for example, every 30 days)
Time-based by key date (for example, every 30 days on the 30th day of the month)
Time-based by factory calendar (for example, every 30 working days)
Q 9 - When you create a maintenance strategy plan for a Printer to be performed after 1 million copies, it is example of?
Answer : B
Q 10 - In Plant Maintenance, you can make a location field as mandatory in IW31 T-Code?
Answer : A
Explanation
Yes, in T-code: IW31 → Location → Location Tab (Mandatory)
Plant Maintenance and Customer Service → Maintenance and Service Processing → Maintenance and Service Orders → Define Field Selection for Order Header Data
(PM)--- Field Selection for Location/Account Assignment Data