Following quiz provides Multiple Choice Questions (MCQs) related to SAP PP. You will have to read all the given answers and click over the correct answer. If you are not sure about the answer then you can check the answer using Show Answer button. You can use Next Quiz button to check new set of questions in the quiz.

Questions and Answers

Q 1 - In which of the Production type, produce materials changed with each lot and costs are calculated as per orders and lots?

A - Repetitive production

B - Discrete Production

C - Manufacturing Production

D - Material Requirement Planning

Answer : B

Explanation

Discrete production is known as industry where produce materials changed with each lot and costs are calculated as per orders and lots.

In Repetitive production, product is not changed for longer time period and production is done as total quantity and not in the form of individual lots.

Q 2 - When you specially tailor the make-to-order production of products as per requirements of the customers, which of the following BOM can be used?

A - Material BOM

B - Cost BOM

C - Equipment BOM

D - Sales Order BOM

Answer : D

Explanation

Sales Order BOM is used when you specially tailor the make-to-order production of products as per requirements of the customers. To meet the customer requirements, you make sales order specific modifications to various assemblies.

Q 3 - To create routing it is mandate that you first define work center?

A - True

B - False

Answer : A

Q 4 - Which of the following movement type is used for Goods Receipt in to Warehouse?

A - 101

B - 102

B - 103

B - 122

Answer : A

Q 5 - Long Term Planning is not actual run but is used to see if all capacity requirement can be fulfilled and you can also transfer simulative area to operative area if requirements are fulfilled?

A - True

B - False

Answer : A

Explanation

Long term planning in SAP PP is used to check future demands at all Bill of Material level. You can check the current capacity and vendor ability to provide the material in required time period.

This is not actual run but is used to see if all capacity requirement can be fulfilled and you can also transfer simulative area to operative area if requirements are fulfilled.

Q 6 - Which of the following Order type is used to define the material to be produced, plant location where production has to be done, date and time, quantity of goods required?

A - Production Order

B - Planned Order

C - Purchase Order

D - Sales Order

Answer : A

Explanation

A Production order is used to define the material to be produced, plant location where production has to be done, date and time of production, quantity of goods required. A Production Order also defines which components and sequence of operations are to be used and how the order costs are to be settled.

Answer : B

Explanation

NetChange in planning horizon −

This run considers the requirement in predefined planning horizon and not like net change which check the future requirements.

In this run, system consider only those material which has undergone some changes from their last MRP run.

Q 8 - When raw material is consumed to produce material as per Production order, to perform goods issue movement type is?

A - 251

B - 101

C - 261

D - 103

Answer : C

Explanation

In SAP PP, goods issue is done when raw material is consumed to produce material as per Production order. When goods are issued, system decreases the inventory of components at the storage location in Production Planning system.

Movement type 261 is used for goods issue.

Q 9 - Material Requirement Planning can be performed at?

A - Single Item single Level & Plant

B - Routing Level

C - None of the above

D - All of these

Answer : A

Q 10 - To set your PIR version active, which of the below value should be used to specify requirement would be considered in material requirement planning?

A - 00

B - 01

C - 02

D - 03

Answer : A

Explanation

In SAP PP, demand management is performed by Planned Independent requirement PIR. Planned Independent requirement provides input for production planning. A PIR contains one planned quantity of product and one date for material or a planned quantity is split over a span of time period.

To set your PIR version active use value 00 to specify requirement would be considered in material requirement planning. To maintain number of versions of planned independent requirement, you can set some numbers to active and others to inactive.

sap_pp_questions_answers.htm